Liquidated Damages
Provisions Generally
Typically, courts in Ohio (and elsewhere) follow a well-known
principle of interpreting contract language so as to carry out the intent of
the parties, when that intent is evidenced by clear, contract language. This is
especially true in commercial settings where courts deem each party on equal footing,
able to secure counsel and able to understand sophisticated business principles.
In other words, courts will generally uphold language in commercial contracts,
unless contrary to statutory law or public policy. Consequently, commercial parties
have a lot of leeway in allocating the risk of a particular deal. One way
parties to a contract allocate risk is to insert a “liquidated damages”
provision into a contract.
“Simply stated, liquidated damages are damages that the parties to a
contract agree upon, or stipulate to, as the actual damages that will result
from a future breach of the contract. The effect of a clause for stipulated
damages in a contract is to substitute the amount agreed upon as liquidated
damages for the actual damages resulting from breach of the contract, and
thereby prevent a controversy between the parties as to the amount of damages.”
The law in Ohio and elsewhere
regarding liquidated damages provisions in real estate and construction contracts
is that when they are fair and reasonable attempts to fix just compensation for
anticipated loss caused by breach of contract, they are enforced;
alternatively, when they are penalties, or punishments for default, they are
not enforced. The difficult problem, in each case, is to determine whether or
not the stipulated sum is an unenforceable penalty or an enforceable provision
for liquidated damages.
Enforceable Liquidated Damages Provision or Unenforceable Penalty-The 3
Part Test
To help provide guidance, the Supreme Court of
Ohio in Samson Sales, 12 Ohio St.3d at 28, 465 N.E.2d 392 set forth a
three-part test to determine whether a contractual provision should be
considered an enforceable liquidated-damages provision or an unenforceable
penalty. The court held: “Where the
parties have agreed on the amount of damages, ascertained by estimation and
adjustment, and have expressed this agreement in clear and unambiguous terms,
the amount so fixed should be treated as liquidated damages and not as a
penalty, if the damages would be (1) uncertain as to amount and difficult of
proof, and if (2) the contract as a whole is not so manifestly unconscionable,
unreasonable, and disproportionate in amount as to justify the conclusion that
it does not express the true intention of the parties, and if (3) the contract
is consistent with the conclusion that it was the intention of the parties that
damages in the amount stated should follow the breach thereof. For example,
a clearly written provision in a $300,000 construction contract between private
parties calling for liquidated damages of $150,000 for not completing the building
on time would probably be held as a penalty because the penalty is unfairly disproportionate
to the amount of the contract.
What about Liquidated Damages Provisions in Public-Works-Construction Contracts?
(Boone
Coleman Constr., Inc. v. Piketon, Slip Opinion No. 2016-Ohio-628)
Should public contracts be
interpreted any different? Should the “Samson
Test” be applied in public as well as private contracts? What if a seemingly
fair liquidated damages provision of $700/day for each day late (measured at
the beginning of a contract) seems not so fair when measured at the end of the
contract because of a 365 day delay? Would that be a penalty or a fair measure
of liquidated damages? These were the issues recently faced by the Ohio Supreme
Court in “Boone”.
The facts of the case seem simple
and straight forward. In 2007, appellant, the Village
of Piketon , solicited bids for the
“Pike Hill Roadway and Related Improvements” project (for the installation of a
traffic light and roadway improvements at the intersection of U.S. Route 23 and
Market Street in Piketon). Appellee, Boone Coleman Construction, Inc.
submitted the lowest bid and was hired for the project. The parties entered
into a contract in which Piketon agreed to pay Boone Coleman $683,300 to complete
the work. The contract expressly provided that the time was “of the essence”
with regard to completion of the project. A liquidated-damages clause provided
that Boone Coleman would pay $700 to Piketon for each day after the specified
completion date (120 days after contract signing) that the contract was not
substantially completed. The contract provided, in pertinent part: “OWNER and CONTRACTOR agree that as
liquidated damages for delay (but not as a penalty), CONTRACTOR shall pay OWNER
$700.00 for each day that expires after the time specified in paragraph 4.02
for Substantial Completion until the Work is substantially complete”.
Boone Coleman did not complete
the project until July 2, 2009― over a year after the parties’ extended the
completion date. Boone Coleman brought suit against Piketon in the Pike
County Common Pleas Court , alleging, among other
things that Piketon had improperly failed to pay $147,477 of the contract price
for the construction. Piketon counterclaimed for liquidated damages. The trial
court granted Piketon’s motion for summary judgment, awarding Piketon $277,900
in liquidated damages. Boone Coleman appealed, asserting that the trial court
erred in awarding Piketon liquidated damages. The appellate court agreed. They
applied the Samson Test but found the
$277,900 in liquidated damages was clearly disproportionate to the $683,000
contract price. Piketon then appealed to the Ohio Supreme Court who overruled
the appellate court and upheld the applicable provision for liquidated damages
of $700 per day for delay of completion.
The Ohio Supreme Court also
applied the Samson Test in Boone and agreed that the appellate
court properly applied the first and third parts of the test. The appellate
court properly recognized that “the
damages incurred as a result of a delay [by Boone Coleman in completing the
project] were uncertain as to amount and difficult to prove” and that “the
plain and unambiguous language of the liquidated damages clause is consistent
with the conclusion that the parties intended that damages in the amount of
$700 per day would follow the contractor’s breach of the project completion
deadline.”
The Supreme Court of Ohio,
however, disagreed that the 2nd prong of the Samson Test (regarding disparity between the liquidated damages and
contract amount) was properly applied by the appellate court. According to the
Ohio Supreme Court, “The correct analysis
looks at whether it was conscionable to assess $700 per day in liquidated
damages for each day that the contract was not completed, rather than looking
at the aggregate amount of the damages awarded [after the fact].” In other
words, the Ohio Supreme Court directs us to look at the per diem damage amount,
prospectively, rather than the total sum, after the fact (which the appellate
court focused on).
Also important to the court in Boone overturning the appellate court’s
decision is the nature of public vs. private construction contracts. Every Ohio-funded
public-improvement construction contract, for example is required by the Ohio
Revised Code to include a liquidated-damages provision. (See O.R.C. Section 153.19). In other words, liquidated damages
provisions in public contracts are seemingly more appropriate because they are
sanctioned by the Ohio General Assembly. Moreover, the Ohio Supreme Court
recognized that contractors in public works contracts need to answer to a
“higher authority”; the public. As stated by the Supreme Court in Boone, “We recognize that liquidated-damages provisions in public construction
projects play an important civic purpose in that they help foster timely
completion of the project, thereby avoiding the loss of billions of taxpayers’
dollars caused by contractors’ delays.” In other words, (according to the
court), “the protection of the public
interest is a proper consideration in determining [the] validity of a
liquidated damages provision.”
Finally, important to the court’s holding was the fact that
the liquidated damages clause in Boone
was a per diem amount vs. a lump sum, and “in failing to recognize this distinction, the
appellate court committed its second error.” Citing precedent, the Ohio
Supreme Court in Boone stated, “[T]he agreement to pay a specified sum
weekly during the failure of the party to perform the work, partakes much more
of the character of liquidated damages than the reservation of a sum in gross.”
What is the moral of this story? To quote Benjamin Franklin (as
cited by the court), “Time is Money.”
In other words, caveat public contractor.
Watch your language with liquidated damages clauses in public works
contracts. Reasonable, per diem liquidated damages set at the outset are likely
to be enforceable, even if they total, at the end, a disproportionate amount to
the original contract price.
No comments :
Post a Comment